Sewer Extension Projects

Hollywood Hills Sewer Extension Project


Public Meetings- Video of meetings:


Project Overview: We are excited to introduce the Hollywood Hills Sewer Extension Project, an initiative focused on enhancing the sewer system in the area from Park Road to 35th Avenue, and Taft Street to Arthur Street. Please contact us to determine if your property will be included in the sewer extension project.

Project Scope:

  • Extending the sewer system within the boundaries of North Park Road (west), North 35th Avenue (east), Taft Street (north), and Arthur Street (south).
  • Installation of approximately 11,380 linear feet of various-size sanitary sewer mains.
  • Placement of 62 maintenance access structures.
  • Integration of 135 laterals with cleanouts for efficient maintenance.
  • Pavement restoration, including temporary installation within two weeks of cleanout runs and permanent paving at the project's conclusion.
  • Monthly field resident meetings on the 1st Thursday of each month for updates and community engagement.
  • Regular correspondence letters to keep residents informed.

Financial Support: There are additional costs for septic-to-sewer conversion. Financial assistance may be available through the Community Development Division, utilizing CDBG funds for septic tank abandonment and sewer lateral pipe installation on private property.

Contact Information: For any resident issues, complaints, or general information, please call (954) 745-0567 x 304 or email hollywoodhills.sewer@brizaga.com.

Thank you for your cooperation and understanding as we work together to improve and enhance our community's infrastructure.