Posted on: August 5, 2022

[ARCHIVED] Traffic Alert: N. Park Road Sidewalk & Roadway Improvement and S. 52nd Ave Paving Project

Traffic Alert

Full Roadway Closures Planned for S. 52nd Ave just south of Washington Street  

Portions of S. 52nd Ave. just south of Washington Street and the roundabout that was constructed on Hillcrest Drive and its intersection with Parkview Drive will be closing fully while drainage and paving work is being done. Work will be done in a phased approach with an anticipated roadway closure schedule as follows: 

The drainage work and its associated trench restoration schedule is as follows:

Phase 

Duration (days) 

Start Date 

Finish Date 

Phase 1 

24 

7/18/2022 

8/19/2022 

Phase 2 

10 

8/22/2022 

9/5/2022 

Phase 3 

12 

9/6/2022 

9/22/2022 

Phase 4 

17 

9/23/2022 

10/18/2022 

 

Please note: this schedule does not include the removal and replacement of the concrete driveways, sidewalk installations, curb installations, milling and resurfacing of the intersection or pavement striping and signage. Motorist should seek an alternate route around full roadway closures to avoid delays. Flagmen and detours will be in place to re-route traffic around the construction zone. 

Roadway & Sidewalk Improvements

Construction has begun along North Park Road between Sheridan Street and Oak Drive near TY Park. This construction project includes swale restoration, milling and resurfacing of the
existing roadway, new pavement markings, and sidewalk replacement.
Access to all properties will be maintained, however the new concrete will take time to cure so immediate access to driveways and sidewalks will be limited after concrete placement. In order to accommodate any inconvenience this may cause, temporary parking in the swale adjacent to private property will be permitted. It is anticipate driveway closures will not last longer than 48 hours.
The City, Weekley Asphalt, and Tectonic Group International appreciates your patience during this community improvement. FOr questions, please contract:
Mark Shirajan
CEI Project Administrator
(786) 246-4438
mark.shirajan@tecgi.com
Navid Afshar
CEI Senior Inspector 
(561) 289-7191
navid.afshar@tecgi.com
Mike Vlam
Contractor Project Manager
(954) 444-1059
mike@weekleyasp.com

Facebook Twitter Email

Other News in City News Updates

Gateway n Neighbor Signage Project WEB

Share your Preferred Design Feedback

Posted on: March 23, 2023
City Property for Sale

City-owned Homes For Sale

Posted on: March 10, 2023
Summer-Camp-Register-WEB (002)

Summer Camp 2023

Posted on: March 20, 2023
Calling-All-Artist-WEB

CALL FOR ARTISTS and CRAFTERS

Posted on: March 9, 2023
Sea Turtle Nesting Season

Sea Turtle Nesting Season

Posted on: February 28, 2023
Spring Break 2018

Spring Break 2023 in Hollywood, Florida

Posted on: February 10, 2023
Online Services

City Services Available Online

Posted on: December 20, 2022
Brd Home Buyer Purchase Assist Program 3 Image

Home Buyer Purchase Assistance

Posted on: July 20, 2022
Hollywood is Hiring Apply Today WEB 2

Turn Your Passion Into a Career!

Posted on: February 15, 2022
Planning and Development Board Minutes

Planning & Development Board

Posted on: September 23, 2016